27 February to 12 March 2024 - utilities investigations
From 27 February 2024, a two-week program of night works was undertaken. Carried out between 8pm and 5am, the focus of the work was on utility mapping and road marking.
While two-way traffic was maintained, traffic controllers closed one lane and diverted traffic around the work site.
Motorists were advised to reduce speed and take extra care while moving through the work zone.
North Rocks Road was reinstated by 5am each morning allowing motorists to use the road as usual throughout the day.
Nightwork: 17 February to 30 August 2025
- Allowing contractors to focus on utility location and reconnection and other work, lanes on North Rocks Road, Windsor Road and Church Street leading into the intersection of these roads were closed from 8pm to 5am.
- On other nights, targeted lane closures on North Rocks Road took place, with different lanes closed throughout the evening. Traffic controllers maintained two-way traffic flow.
- Digital message boards were installed highlighting the lane closures, motorists were advised to slow down and proceed with caution while travelling through the work zone.
- North Rocks Road was reinstated by 5am each day.
First weekend closure: Friday 7 February to Monday 10 February 2025
To allow pile installation and other works, a full closure of North Rocks Road between Windsor Road / Church Street and the Woolworths’ driveway at The Mills shopping centre was scheduled. Detours were in place.
A section of North Rocks Road was closed from 8pm Friday to 5am Monday with work taking place 24hrs a day.
- Motorists were able to travel south along North Rocks Road.
- Motorists could turn right into The Mills shopping Centre. On exiting the centre, customers could only turn left – no right turn.
- Access for buses was facilitated.
- Increased truck movements to and from the laydown area (compound) on Bourke Street were managed.
- North Rocks Road was reinstated for normal use by 5am Monday morning.
Nightwork: 17 February to 4 June 2025
Allowing further progress on utilities searches, relocation and reconnection, nightworks from 8pm to 5am were scheduled for five days a week.
- Traffic controllers maintained traffic flow in both directions.
- Controllers were in place at Woolworths’ driveway to ensure access in and out.
- Increased truck movements to and from the laydown area (compound) on Bourke Street were managed.
- North Rocks Road was reinstated for normal use by 5am each day.
Second weekend closure: Friday 11 July to Monday 14 July 2025
Enabling further work on Hunts Creek Bridge, Transport for NSW has approved a full closure of North Rocks Road between Windsor Road / Church Street and the Woolworths’ driveway at The Mills shopping centre. Detours will be in place.
- Work will start at 8pm Friday 11 July, and continue round-the-clock until 5am Monday 14 July.
- Detours will be in place – via Pennant Hills Road, James Ruse Drive and Cumberland Highway. Please refer to the map above.
- Motorists will be able to travel south along North Rocks Road and turn right into The Mills shopping centre.
- Customers will exit left out of the centre. No right turn.
- Traffic controllers will be onsite. Controllers at The Mills shopping centre driveway will facilitate access in and out of the centre.
- Increased truck movements to and from the laydown area (compound) on Bourke Street are to be expected.
- Access through the work zone will be provided for buses and emergency service vehicles.
- North Rocks Road will be reinstated for usual use by 5am Monday 14 July.
- Avoid the area if possible.
- Expect delays.
- Allow extra travel time.
Nightworks mid-July 2025 (dates to be confirmed)
The focus of the two-week activity will be on essential utility cut-overs, including Telstra upgrades. Sydney Water will complete final cut-over activities including chlorination to disinfect the newly-installed water mains to ensure water is safe to drink. Jemena will relocate the gas mains.
Work will start at 8pm with North Rocks Road reinstated to usual conditions by 5am the next morning. Traffic controllers will be on site to manage traffic flow. Two-way traffic will be maintained.
It is expected that night work will be schedule up to four (4) nights a week.
Schedule subject to the successful completion of works during the weekend closure, TfNSW approval, weather and site conditions.
Third weekend closure
15 to 18 August 2025
Full closure of North Rocks Road between Windsor Road / Church Street and the Woolworths’ driveway at The Mills shopping centre.
- Dates to be confirmed, subject to the completion of nightworks including the relocation and reconnection of utilities and approval from Transport for NSW.
- Detours in place. Refer to the map above.
- More information to be provided.
Fourth weekend closure
Late-2025 (dates to be confirmed)
Full closure of North Rocks Road between Windsor Road / Church Street and the Woolworths’ driveway at The Mills shopping centre.
- Dates to be confirmed by Transport for NSW.
- Detours in place. Refer to the map above.
- More information to be provided.
Stage 1
One-month closure of North Rocks Road (north bound)
Late-2025 (dates to be confirmed)
North Rocks Road will be closed from the intersection of Church Street and Windsor Road to the Woolworths’s driveway at The Mills shopping centre.
- The program is subject to the successful completion of the nightworks and the weekend closures in addition to approval from Transport for NSW.
- Detours will be in place (refer to the map above).
- Work will take place Monday to Friday 7am to 5pm and Saturdays 8am to 1pm, with some nightwork from 8pm to 5am as required.
- Motorists will still be able to travel south along North Rocks Road and through to Church Street and Windsor Road, as well as turn right into Woolworths at The Mills shopping centre.
- Customers will exit left out of the shopping centre. No right turn.
- Access through the work zone will be facilitated for buses and emergency service vehicles.
- Avoid the area if possible.
- Expect delays.
- Allow extra travel time.
Stage 2
Late-2025/early-2026 (dates to be confirmed)
- North Rocks Road is open to traffic.
- No detour in place.
- One (1) lane in both directions will be open – two-way traffic maintained by traffic controllers.
- Work will take place Monday to Friday 7am to 5pm and Saturdays 8am to 1pm.
- Avoid the area if possible.
- Expect delays.
- Allow extra travel time
- More information to be provided.
Stage 3
February 2026 – March 2026 (dates to be confirmed)
- North Rocks Road open - traffic maintained in both directions by traffic controllers.
- Work will take place Monday to Friday 7am to 5pm and Saturdays 8am to 1pm with additional nightshifts and weekend work if required.
- Traffic control in place at Woolworths’ driveway at The Mills shopping centre to ensure access in and out.
- Increased truck movements to and from the laydown area (compound) on Bourke Street.
- Expect delays.
- Allow extra travel time.
- More information to be provided.
Please download the (PDF, 160KB)Hunts Creek Bridge program(PDF, 136KB).