April update - nightwork extended to June 2025
Nightwork on Hunts Creek Bridge, planned to end in April, is now extended to June due to unexpected finds.
While extensive utility searches were undertaken, differences in the ground conditions and the actual location of services on site - compared to our underground investigations work - is further complicating the complex relocation and reconnection of utilities planned for this phase of the project.
As nightwork continues, two-way traffic will be maintained. Nightwork will take place from 8pm. North Rocks Road will be reinstated by 5am each day.
Weekend closures of North Rocks Road - with detours - are now expected to be staged in June and July. However, this schedule will be subject to completion of the utility relocation work.
Further updates, including dates of the closures, will be provided as soon as a new program is confirmed.
Contact us
Please contact the project team should you have any questions. Call City of Parramatta’s Customer Service Centre on 1300 617 058 and ask for the Hunts Creek Bridge team or email HuntsCreekBridge@cityofparramatta.nsw.gov.au
For out of hours or urgent construction program issues, call the Abergeldie Project Team on 0400 374 779, or email huntscreekbridge@abergeldie.com
For live traffic updates - visit livetraffic.com.
Arrangements for buses
Council has worked with Transport for NSW to find a solution for buses. Buses will be able to access North Rocks Road (through the construction site in both directions) during all stages of the project.
For the full program, download our PDF.
Detours will be in place on selected weekends in June and July 2025 (subject to the completion of night works). North Rocks Road will be fully closed from intersection of Church Street, Windsor Road and North Rocks Road, to the Woolworths’ driveway. Detours will be in place. Please note there is a change to the detour from Church Street. Northbound traffic will no longer be able to turn right into Pennant Hills Road.