Five-week closure of North Rocks Road planned for late-October to early-December 2025
The next stage of the Hunts Creek Bridge replacement project will see a five-week closure of North Rocks Road.
The final program will be confirmed by Transport for NSW (TfNSW). However, it is likely that the work will take place late-October to early-December 2025.
North Rocks Road will be closed to northbound traffic from the intersection of Church Street/Windsor Road to the Woolworths’s driveway at The Mills shopping centre.
Motorists will be directed away from the construction site to detours via Pennant Hills Road, James Ruse Drive, and the Cumberland Highway.
During the shutdown, southbound traffic will be able to turn right into The Mills shopping centre and travel through the construction site to turn into Church Street or Windsor Road.
This extended closure will allow accelerated work on the bridge replacement program including:
- Works to the western half of North Rocks Road, removal of the existing culvert, reshaping the creek, and construction of the bridge deck
- Asphalting, line-marking works in preparation for Stage 2 works (eastern side of the bridge).
The community is advised to expect some delays and allow extra travel time.
The schedule is subject to Transport for NSW approval, weather, and site conditions. Further information, including confirmed dates, will follow.
Stage 2 works scheduled for early-December 2025 to late-April 2026
While Transport for NSW is yet to confirm dates, it is likely that Stage 2 works will take place early-December 2025 to late-April 2026.
During this part of the program, there will be no detours in place. Two (2) lanes will be open allowing traffic flow in both directions.
The work will focus on the eastern side of the bridge and include removal of the existing culverts, reshaping the creek, and construction of the bridge deck. As well as asphalting, line-marking, and utility connections.
While most of the work is planned to take place Monday to Friday 7am to 5pm and Saturdays 8am to 1pm, nightworks and weekend work may be required.
The community is advised to expect some delays and allow extra travel time.
The schedule is subject to Transport for NSW approval, weather, and site conditions. Further information, including confirmed dates, will follow.
Stage 3 works scheduled for April to June 2026
While Transport for NSW is yet to confirm dates, it is likely that Stage 3 works will take place from April to June 2026.
The stage of works will see reinstatement of utilities and driveways, line-marking, completion of the bridge and footpath, site clean-up and the re-opening of North Rocks Road. Traffic flow returns to normal.
More information:
Visit livetraffic.com for live traffic updates.
For construction related enquiries, urgent or after-hours enquiries, please contact Abergeldie Contractors on their dedicated community information number 0400 374 779 or email HuntsCreekBridge@cityofparramatta.nsw.gov.au
The schedule is subject to Transport for NSW approval, weather and site conditions. Further information, including confirmed dates, will follow.
Detours
During the weekend shutdown from 8pm Friday 10 October to 5am Monday 13 October 2025, North Rocks Road will be closed from the Church Street / Windsor Road intersection to the Woolworths’ driveway at The Mills shopping centre. Detours will be in place.
The full detour (via Pennant Hills Road, James Ruse Drive and Cumberland Highway) is anticipated to add approximately 20 to 30 minutes to travel time. Please refer to the map below.
Traffic controllers will be on site to manage traffic flow and access to The Mills shopping centre. Motorists are advised to avoid the area if they can, expect delays, and allow extra travel time.
Arrangements for buses and emergency service vehicles
Buses and emergency service vehicles will be able to access North Rocks Road (through the construction site in both directions) during all stages of the project.
Arrangements for large vehicles
To assist with traffic management, Bettington Road and Stratham Avenue can be used by vehicles up to 8-tonnes during the construction period.
Vehicles more than 8-tonnes will be required to use arterial roads that support their loads, i.e. Pennant Hills Road, Cumberland Highway, Windsor Road.
Live Traffic Updates
Visit livetraffic.com for live traffic updates.